Posted on September 29, 2017 by aatkinson

Crews are putting the finishing touches on numerous areas throughout Music Hall, in preparation for its big reveal next week. Drywall hanging is complete and carpet installation is now underway in Corbett Tower. The orchestra risers in Springer Auditorium are being stained, as well as the plywood for the orchestra pit. The marble flooring in the Main Lobby is being cleaned, and flooring in the lounge has been completely installed. New sidewalks have been poured outside the Hall, as well as a lane to accommodate limousines. To look back on this amazing journey, check out the Project Update Archive.