Posted on January 30, 2018 by aatkinson
Crews continue making great strides at the Court & Walnut project site. The majority of current work remains focused on the basement area, as excavation continues and pile caps are being poured. The pouring and forming of the basement walls is underway, and waterproofing is ongoing. In the coming weeks, crews will begin pouring and forming the basement columns. On the first floor, pile caps and grade beams are also being poured, and crews will begin pouring and forming columns and walls in the coming weeks. For additional details, subscribe to regular project updates, and refer to the archive for past updates.