project-update 9216
Posted on January 2, 2018 by aatkinson
Crews remain hard at work at Rennen and Beecher Flats. Foundation piles have been drilled and work on the pile caps and grade beams will begin in the coming days. Currently, the mason is onsite to infill the openings in the existing building at 1505 Race Street. Once the foundations, grade beams, and building slabs are complete, framing work will begin, and Rennen and Beecher Flats will start to take shape.