Posted on July 25, 2017 by aatkinson

Despite the heat and humidity, crew have continued to make exceptional progress both inside and outside the Hall. Both the CAA and CSO offices are nearing completion. A variety of work is ongoing in the Main Lobby, where the floors have been completely demolished to make way for the new bars located in the North and South Circulation Areas. Final paint is complete on the Main Lobby ceiling, and vestibule drywall work is underway. Various work on the stage inside Springer Auditorium continues, in addition to carpet and light fixture installation. Lastly, plaster work has begun on the walls in Corbett Tower. For additional details, subscribe to regular project updates, and refer to the archive for past updates.