project-update 8540

Posted on June 30, 2017 by aatkinson

Crews continue to work at a steady pace, making great progress throughout the Hall. This past month, the stage floor in Springer Auditorium was demolished, and plywood for the pit at the front of the stage was installed. In addition, various light fixtures were hung and the chandelier was re-installed. Meanwhile, paint and plaster work is ongoing in the Main Lobby, as construction of the spotlight room and stenciling of the ceiling have resumed in Corbett Tower. On the building’s exterior, brick staining is now complete on the Elm Street façade. Concrete pours for the sidewalks are underway. For additional details, subscribe to regular project updates, and refer to the archive for past updates.