project-update 8438
Posted on May 31, 2017 by aatkinson
The masonry stair tower has progressed up to the fourth floor at the 15th and Vine project, and is scheduled to be completed next month. Additionally, steel delivery is set to begin during the first week of June. Once it’s on site, the building’s steel will be erected beginning at the south end of the site, progressing to the full height of the structure, and then moving north. Finally, in addition to continuing to work on the electric trench, engineers are coordinating mechanical systems utilizing Building Information Modeling (BIM) technology, which creates a 3D representation of the structure to make coordination easier. Leasing information for the office and retail space is available on the 3CDC website.