project-update 8286

Posted on April 28, 2017 by aatkinson

Over the course of the last month, work on the Glassmeyer condominium building has moved along at a steady pace. The exterior of the building is starting to take shape as brand new windows have been installed, roof work is complete, and exterior trim work is underway. Inside the building, the mechanical, electrical and plumbing systems are roughly 50% complete, with insulation and drywall currently being installed in these areas. In the courtyard, crews are nearly finished framing the balconies and are beginning work on the exterior stairwell.