project-update 8027

Posted on March 31, 2017 by aatkinson

Construction continues to progress at the future headquarters of Empower MediaMarketing. All floors have now been poured. Interior plumbing and electrical rough-ins are in process, beginning on the first floor. Exterior framing has begun at the southwest corner of the building and interior framing has started around the interior stairs, restrooms, and electrical rooms. Construction remains on target, with an expected completion date of August 2017.