project-update 7229

Posted on November 30, 2016 by aatkinson

Empower MediaMarketing’s new location continues to make steady progress. As of this month, all foundation work has been completed, as well as the elevator shaft. Construction crews have successfully removed the roof and all interior floors of the historic Hukon Building, and an elaborate scaffolding system is now underway. It will allow the demolition of the interior to begin. There is a crane on-site and steel erection has begun at the southwest corner of the project site. This will allow the building to officially “come out of the ground.” Steel erection will be the focus of construction from now until early January.