At the future home of Empower MediaMarketing, crews finished installing Geopiers – the deep foundation system used to stabilize the existing soil – in early October, allowing work to begin on the shallow building foundations. In addition, shoring around the four exterior walls of the historic Hukon Building is underway, which will allow for the demolition of the interior of the structure to start in early November. Steel fabrication has also started, and installation will begin in late November.