Posted on March 31, 2016 by jrudemiller
Construction is in full swing at the Race Street Condos, as foundation installation, electrical and plumbing installation, and first-floor structural masonry and steel work were all completed in March. Also on the first floor, a portion of the concrete slab will be poured next week. Meanwhile, on the second floor, joist framing and masonry work are both in progress. Outside the building, the primary façade’s finished masonry work is scheduled to begin in mid-April.