Posted on February 26, 2016 by jrudemiller

Plenty of work is currently underway at Music Hall, which will remain open for performances until May 2016. Demolition in the Cincinnati Symphony Orchestra (CSO)’s office space is substantially complete, allowing crews to begin on under-slab mechanical, engineering and plumbing work in the space. Structural footers for the mezzanine in the new CSO offices are currently being dug in, a process that is expected to last a few weeks. Elsewhere in the building, new passenger elevator pits are being dug in and abatement has continued in the basement and paint shop.