Posted on February 3, 2016 by jrudemiller
At Memorial Hall, the foundation for the addition at the rear of the building is currently under construction. In addition, the windows are being carefully removed and transported off-site for restoration. Inside the building, interior wall openings are being created to accommodate passage into the new addition and the deteriorated ballroom flooring has been removed. Mechanical coordination is also underway.