project-update 5099

Posted on September 1, 2015 by jrudemiller

Parksite is steadily approaching its fall completion date, as work on installing finishes continues. The north side of the building is trimmed and tiled, and cabinets have been installed. The south units are fully framed and drywalled and the inspections of mechanical units are nearing completion. The project is expected to be finished in mid-October.