project-update 5070

Posted on July 30, 2015 by jrudemiller

Work is progressing nicely at the Drop Inn Center Men’s Facility, as drywall has been installed in the staff area on the western half of the first floor and received a first coat of paint. Elsewhere in the building, block-fill is being painted on the block walls in the shelter areas, lighting fixtures are being hung on the first floor, and framing in the new clinic area is complete, and drywall installation has started. Additionally, new framing and support structures surrounding the new courtyard are currently being installed, and the installation of new windows on the building’s exterior is ongoing.