project-update 4999

Posted on June 29, 2015 by jrudemiller

A new opening for the roughly 4,000-square-foot courtyard has been created at the Drop Inn Center Men’s Facility, and construction of the new roof and exterior masonry repairs are currently ongoing. In addition, new windows are being installed on the exterior. Current construction also includes interior masonry work for the last of three shelter areas, drywall hanging, and framing for the new clinic area.