project-update 4935

Posted on May 29, 2015 by jrudemiller

With all foundations in place, framing has commenced for the new townhomes being built as part of the third phase of the Mercer Commons project. Framing is scheduled to be complete by mid-June, after which window installation, exterior trim, and masonry will get underway. The 14 Mercer Street renovation is fully framed and drywall is nearing completion. In addition, interior finishes will begin by mid-June. Construction is still expected to be complete by late fall 2015.