Posted on May 28, 2015 by jrudemiller
Preparations to open the roof over the new 4,000-square-foot courtyard are underway at the Drop Inn Center Men’s Facility, as crews continue to work on completing the new roof and exterior masonry repairs. In addition, interior concrete repairs and steel framing are nearly finished, drywall hanging has started in the new shelter areas, and basement bathroom fixtures are in the process of being installed. The shelter is scheduled to be finished in September 2015.