Construction is well underway at the new Start-up Innovation Hub at 1311-1315 Vine. Current construction includes structural work in the sub-basement, concrete foundation pours, interior framing, and mechanical, electric, and plumbing rough-ins. Project completion is targeted for June of 2015.