Posted on February 13, 2015 by jrudemiller
The epoxy coating of the floor is ongoing at Building 1 of City Gospel Mission’s future campus, while paint and drywall touchups are being finalized on the second floor. Also, the building’s kitchen equipment is set to be delivered later this month. At Building 2, the installation of bar joists for the roof is ongoing, and decking is scheduled to be completed this month. Meanwhile, rough-ins continue on all floors.