Posted on January 15, 2015 by jrudemiller

The dunnhumby Centre Garage has now been open to the public for nearly two months, although a few finishing touches are currently being implemented. Additionally, of portion of level four is being used for construction storage and, therefore, is closed to the public. Elsewhere at the site, the area where the buck hoist sat is now completely buttoned up and the building’s façade is now complete. Outside the building, a portion of the east sidewalk is closed while work is being done on the Duke Energy vault beneath the sidewalk. Also, the site’s light poles have started going up along the sidewalk around the building.