Posted on December 15, 2014 by jrudemiller

Work is progressing nicely at City Gospel Mission’s two-building campus. In Building 1, the new roof is now complete, and the curb and asphalt base has been set. Inside, the drywall is being finished on the first floor and the second floor has its first coat of paint. At Building 2, the second-floor steel work is ongoing and the third-floor deck will be poured this week. Layout on first floor started in earlier this month.