project-update 4222

Posted on September 11, 2014 by jrudemiller

Concrete construction is now complete. Construction of the Mechanical, electrical and plumbing installations continue on all finished site levels – both above and below grade. Construction of the parking garage elevators has continued below and above grade up to level five. Setting of the building façade panels has reached level nine, while exterior glazing for the façade and installation of wire mesh is still ongoing. Construction of the storefront on the south side of the building along Fifth Street is underway. Work on the interior of the building has continued, including the hanging of drywall on level one and the installation of waterproofing on the lower levels.