Concrete construction has now reached the roof. Construction on the north core elevator shaft has reached level eight, while work on the south core elevator shaft is now complete. Concrete pours for the building’s columns have reached level nine in the northern half, and have been completed in the southern half. The concrete parking garage stairs have been poured and cured up to levels four and three in the south and north cores, respectively. The concrete slab is complete to level eight throughout the building, and to level nine in the southern half. Mechanical, electrical and plumbing installations continue on all finished site levels – both above and below grade. Setting of the building façade panels remains ongoing, while exterior glazing for the façade has begun. Work on the interior of the building has started, including the hanging of drywall on level one and the installation of waterproofing on the lower levels.