Posted on July 14, 2014 by usdp

Concrete construction has now reached level nine. Construction on the north core elevator shaft has reached grade level seven, while work on the south core elevator shaft is now up to grade level nine. Underground elevator construction is also underway. Concrete pours for the columns in the northern and southern areas of the site are complete up to levels six and eight. The level six and eight concrete slabs located throughout the site are also complete. Mechanical, electrical and plumbing installations continued on all finished site levels – both above and below grade. Setting of the building façade panels remains ongoing.