Concrete construction has now reached above grade to level eight. Construction on the north core elevator shaft is has reached grade level six, while work on the south core elevator shaft is now up to grade level eight. Underground elevator construction is also underway. Concrete pours for the columns in the northern and southern areas of the site are complete, up to levels five and seven. The level five and seven concrete slabs located throughout the site are also complete. Mechanical, electrical and plumbing installations continued on all finished site levels. Preparation for laying the building façade is now underway. Underground unit construction will remain ongoing throughout the site.