Concrete construction has now reached above grade to level six. Concrete pours for the columns in the northern and southern areas of the site are complete, up to levels three and five. The level four and five concrete slabs located throughout the site are also complete. Concrete stairs have been poured and cured in the north and south core elevator shafts, while construction work on the supply elevator remains ongoing. Mechanical, electrical and plumbing installations continued on all finished site levels. Underground unit construction will also continue throughout the site.