Posted on April 8, 2014 by usdp

Concrete construction has continued above grade up to level five. Speed ramp construction is one hundred percent complete up to level three. The construction of the north core elevator shaft is complete up to level three. Construction of the south core elevator shaft is complete up to level five. Concrete pours for the columns in the northern half of the project are one hundred percent complete up to level two. Concrete pours for the columns in the southern half of the project are complete up to level three. The level three concrete slab is one hundred percent complete. The level four concrete slab is one hundred percent complete in the southern half of the project. Waterproofing around the perimeter of the project is now complete up to level one along with the backfill.
There is continued interest in the commercial space at street level, and 3CDC staff is currently reviewing business plans.