project-update 3572

Posted on February 20, 2014 by amileham

Concrete construction has continued above grade up to level 3. Construction of the garage speed ramp is now above grade and 100% complete up to level 2. Decking and form work continues. The “martini glass” columns for the first floor are 100% complete and illustrate the full ceiling height of this ground floor commercial space. A full-scale mock up of the façade for the project is nearly complete and can be viewed along the Fifth Street side. Construction of mechanical, electrical, and plumbing continues below grade and is roughly 15% complete. Backfill up to level 1 is expected to be complete by the end of February.