project-update 3526

Posted on January 9, 2014 by amileham

Concrete construction is officially above grade, and decking and form work for level two continues. Level 2 is 25% complete, and the columns and structure for the first floor commercial space is roughly 50% complete. Mechanical, electrical, and plumbing work have commenced on the below grade portion of the project. Site utilities, including gas and electric, are in place to be used for the entire project. The building ‘skin’ has been purchased and a full-scale mock-up is expected to be in place by the end of the month.