Posted on November 14, 2013 by amileham
Build-out of the approximately 40-seat restaurant is about 33% complete and the restaurant is scheduled to be open early December. Plumbing and Electric rough-ins are complete and the hood is installed; HVAC crews are onsite now. Finishes such as banquettes and bar millwork are being fabricated offsite and will begin arriving onsite the first week in November.