At August Flats, cabinets, flooring and tile have been installed. Countertop installation is nearly complete, as well, while trim work is ongoing. HVAC, plumbing and electrical finishing work continues. The Race Street sidewalk has been replaced and replacement of the Green Street sidewalk is underway. Storefront framing and glass installation is in progress.