Posted on April 3, 2023 by aatkinson
At The Foundry, interior finishes and artwork are nearing completion at the Five Iron Golf space. Audio/Visual and IT installation is in progress and a punch walk will be scheduled in the coming weeks.
Work continues to progress at the new office of Divisions Maintenance Group (DMG). The monumental stair was delivered and has been set in place. The installation team will weld it back together in the coming days. The installation of millwork and countertops is ongoing, while specialty wall finishes are beginning. Carpet installation is nearly complete. DMG’s systems furniture is scheduled to be installed in the coming days. DMG’s AV vendor mobilized last month and is currently installing their sound masking system. They are also getting started on infostructure and presentation areas. Lastly, the exterior signage package has been released for fabrication. Installation will happen in phases and should be completed later this month.