At The Foundry, work on the Five Iron Golf Space has made substantial progress over the last month. Millwork continues at the simulator bays and prepped locations continue to be painted. Overhead and bar lighting are being installed, as well as tile in the restrooms. Kitchen and bar equipment is also being installed as it arrives on site and bar tops are being prepped for installation. All designated areas of concrete have been polished. Finally, demising wall work has begun outside of the west wall.

The future home of Divisions Maintenance Group’s (DMG) office is coming along. Drywall finishing work continues throughout the space, as well as the installation of the internal storefront glass. Millwork has been delivered for the third-floor café, and installation is underway. Specialty wall coverings are also being installed, beginning on the third floor. The monumental supplemental stair steel was delivered and staged on site, and installation has begun. Installation of the monumental stair itself will begin once the steel installation is complete.