project-update 17247

Posted on January 31, 2023 by aatkinson

Drywall and plaster repair work is largely complete at August Flats. The installation of bathroom tile continues, and other flooring work is also underway. Crews will begin installing plumbing and electrical fixtures in the coming weeks.