project-update 17247
Posted on January 31, 2023 by aatkinson
Drywall and plaster repair work is largely complete at August Flats. The installation of bathroom tile continues, and other flooring work is also underway. Crews will begin installing plumbing and electrical fixtures in the coming weeks.