project-update 17244
Posted on January 31, 2023 by aatkinson
At The Foundry, the future home of Five Iron Golf is well underway with walls 90% closed and drywall skimming underway. The overhead work for the bar has begun and sections of the finished walls have received primer. Prep work for the epoxy flooring recently began and exterior concrete work is now complete.
Divisions Maintenance Group (DMG)’s new office space has made considerable progress. Final roof and penetration work are complete as several other tasks continue, such as the hanging of hard lid ceilings and painting throughout the space. Electrical work is underway on all floors, restroom tile installation has begun and DMG has started maintenance and renovations for their dedicated elevator. In the coming weeks, casework installation, storefront glass installation and electrical tie-in work will begin. Lastly, DMG’s exterior sign package is officially in for permit.