project-update 17107

Posted on January 3, 2023 by aatkinson

At the Five Iron Golf space, rough inspections have been completed. Moisture board has been installed at all restroom and locker room locations and fire-rated plywood is being installed at the simulator pod locations. Exterior concrete work has been scheduled. Additionally, the location for the grease interceptor has been determined.