Interior drywall is being installed and finished in Divisions Maintenance Group’s new office space, with painting to follow. This will allow electrical and plumbing fixtures to begin being installed, as well as HVAC and fire protection trim out to occur.

At the future home of Five Iron Golf, framing is complete. Plumbing and electric rough-in inspections are being scheduled. Drywall will follow the inspections.