A variety of work is underway at Avril Lofts. Tile is being installed in the fourth-floor condos, while walls are being painted in the third-floor condo units. On the second floor, framing is officially complete and ready for drywall. The building will receive permanent power in the next few weeks and HVAC systems will be turned on, allowing wood floors to be installed. Structural stabilization of the first-floor Avril Bleh market space is complete and ready for drywall and a new walk-in freezer and grease duct.