project-update 15399

Posted on January 31, 2022 by aatkinson

The Willkommen project continues to push closer to completion as construction continues in the new buildings at 1521 Vine Street, 1512 Republic Street and 1602 Pleasant Street. Wood flooring, furnaces, bathtubs and tile are being installed in the buildings on Vine Street while final touches and exterior brickwork are wrapping up at 1512 Republic Street. The installation of cabinetry, appliances and bathroom tile continues in the residential units on Pleasant Street.
Construction is officially complete at several of the buildings on Liberty, Walnut, Woodward, Race, Moore and 15th Streets, as well as at 1604 and 1606 Pleasant Street. At 1601 Race Street, the renovation of the Alabama Fish Bar is complete, and the restaurant has reopened its doors.