Posted on December 29, 2021 by aatkinson

Streetscape work on 5th Street is now complete, and the sidewalk and street have been reopened. The installation of cornice metal panels is ongoing, as work continues at the corner of Vine and 5th streets, as well as on Vine and Race streets. The streetscapes at Race and Vine will be complete and reopened in January when work on the metal panels has wrapped up. The garage and office lobbies have been completed and opened, and Deloitte opened its doors to employees on December 13 as the first tenant to occupy the building. Meanwhile, crews have begun framing in the future home of Royce – a corner restaurant at 5th and Vine. Interior fit out work continues in the Turner office space at the west side of the second floor and plans for the Jeff Ruby space on Vine Street have been submitted for permit.