project-update 15293

Posted on December 1, 2021 by sujvary

Office furniture is being installed in Deloitte’s suite at The Foundry. Walls are being framed for Turner’s suite, and both restaurant tenants are awaiting various permits. Interior work on the core shell is complete, and the streetscape work along Race and 5th streets is complete, with similar work underway along Vine Street.