project-update 14618

Posted on August 31, 2021 by sujvary

The three buildings that make up Keyer Row are set to be completed in mid-November and early December. Framework on the street-level storefront of the southern-most building is underway, while the roof of the center building was prepped for skylight installation at the end of August. Plumbing inspections for the north building were set for the end of August, and drywall work is wrapping up inside four residential units.