At the Foundry, façade work has been completed along both Vine and Fifth streets, and is underway on Race Street. The buildout for Deloitte’s recently leased space is continuing, along with framing and drywall installation for the lobby and corridor walls. The roof replacement is expected to be complete in September, and work on the Fifth Street streetscape will begin in the coming weeks.