project-update 14519

Posted on July 30, 2021 by sujvary

In July, The Foundry finished construction on the lower roofs as well as the Level 4 roof. Core shell lighting, sprinkler, ductwork and water source heat pumps are all set throughout the building, and drywall for the lobbies will occur in the coming weeks. Façade work is ongoing, with the new glass façade that will wrap the building completely installed on Vine Street and half installed on Fifth Street. Crews will next move to Race Street and installation is expected to be completed in August. Work along Vine Street’s streetscape will be underway throughout August as well.