project-update 13701

Posted on March 31, 2021 by sujvary

At Gosling Flats, window installation has been completed on both buildings. Drywall has been hung on the first and second floors and drywall finishing has started. Interior painting and work on tile flooring will begin soon. Plumbing is complete at 1508 Race Street and window installation is underway.