The new Fifth Third LED board and sign at the top of The Foundry has been installed and is now in operation. Interior work has kicked off, with core and shell sprinkler piping, electrical conduit and ductwork underway. Roofing work will start in April, as will continuation of mechanical, electrical and plumbing work.