project-update 13409
Posted on January 28, 2021 by sujvary
Construction of the new LED board at The Foundry is underway. Demolition of the existing screen began in early January, and a steel frame has been installed for the new board. In addition, demolition of the façade has been completed, but is still ongoing in the elevator shafts inside the structure. Mechanical, electrical and plumbing work will begin in April, with installation of the new glass façade expected to begin in May.