project-update 13406

Posted on January 28, 2021 by sujvary

Construction on the residential portion of 4th & Race continues with wall-framing, and mechanical, electrical and plumbing work. Residential elevators are nearly finished, and the parking garage and residential lobby entrance canopies have been installed. The temporary overhead protection at the corner of 4th & Elm streets was removed in mid-January, and the buck hoist that helps get construction materials to upper stories will be removed in mid-February.

For additional details, subscribe to regular project updates, and refer to the archive for past updates.