Posted on December 30, 2020 by sujvary

At the Court Street Plaza, trench drains have been installed beneath the westbound lane and will provide drainage in place of a traditional catch basin. Additionally, underground electric work connecting pole bases to pull boxes for traffic signal operation in the western portion of the project has been completed and a subbase, which will act as the foundation for the new sidewalk, has been installed on the western portion of the block. Demolition of the eastbound lane began this past week, and foundations for bollards will be poured in the coming weeks. As a result of the demolition work, the eastbound lane will remain closed to thru traffic until January 8. The westbound lane will be shut down to thru traffic until mid-March.